Hello,
so I am fairly new to running a CMM, and this might just have a simple answer like over looking something in CMM manager..

I run the CMM here at my shop on a Desktop computer with a PH20 head, I'm trying to set up a laptop with our open seat CMM manager so that I can program some things offline on the laptop while its running other things on the desktop. Right now I can't figure out how to Change the head on the laptop from PH10 to PH20. Currently the laptop has CMM-Manager 3.8 SP1 and the Desktop with ph20 has CMM-manager 3.9 SP2. Is the Upgrade the reason I can't change the head? or could it be that I don't have UCC server on the laptop? Am I simply over looking how to change the head in CMM Manager??

If anyone can answer it'd be much appreciated!
Thanks!

User avatar
CrashN8
Site Admin
Site Admin
Posts: 579
Joined: Thu Feb 09, 2017 4:07 pm

Re: Changing The head from PH10 to PH20?

Post by CrashN8 » Thu Oct 15, 2020 5:35 pm

You can change Probe Head from System Ribbon Tab>Machine Setup. In the Probe Tab of Machine Setup, there is a drop down list of all available probes. Select it, then Apply, OK.